Our Approach to Methods of Measurement for Quantity Takeoff

blog-image

From project planning, cost estimating, scheduling, and other project control discussions.

Project Challenges

  • How do you conduct quantity takeoff for construction materials, products, and work tasks?
  • Does your company have a quantity takeoff manual or templates to help guide those assigned to conduct quantity takeoff?
  • Does your company maintain standardized Bluebeam tool sets with tools (subjects) and relevant custom columns for takeoff, organized by item of work and related construction materials, products, and work tasks?
  • What factors define how quantity takeoffs are conducted?
  • Would access to templates of standard methods of measurement for quantity takeoff that are based on each item of work and related work tasks be of any value to you?

Project Context and State-of-Practice

We understand the relationships between items of work, work tasks, construction materials, products, and units of measure (UOM). We also recognize how project control practices focus on these elements. This is where quantity takeoff plays a crucial role.

Let’s be serious; if the quantity takeoff is not accurate, then all other aspects of project controls, such as cost estimates and project scheduling, that depend on it will also be inaccurate.

Here are some of the factors that define how different work tasks, construction materials, and products are measured:

  • Level of detail,
  • Construction material and products measurement practice,
  • Work tasks measurement practice, and
  • Alignment to historical cost data to be referenced

To avoid reworking takeoff due to the use of the wrong UOM, the UOM used for takeoff must match the UOM found in the historical record or past cost for the construction materials, products, and work tasks being measured. This is why the person conducting quantity takeoff must first review and reference past cost records to determine the units of measure to use.

If you are asked to help quantify an item of work composed of several interconnected and dependent work tasks, construction materials, and products, how would you approach solving this problem?

So, here we go. The key point is that each item of work is estimated based on corresponding work tasks, construction materials, and products that drive the price of that item. The work tasks, materials, and products are measured using specific UOM, and the UOM defines the related quantity takeoff dimensions used to calculate the quantities.

For example, the UOM for clear and grub for a vegetated area is ACRE, and this is derived and calculated using set dimensions (length times width, or area) from the drawings.

Having the required work tasks, construction materials, products, their UOM, and related dimensions clearly mapped makes it easy to perform quantity takeoff for an item of work.

Specific Solutions from Our Webbook

Master the fundamentals of heavy civil construction with our webbook—gain solid expertise, practical skills, and help to add value to the organizations you work for.

Below is one example of our approach to simplify quantity takeoff. The template is for a specific item of work and the related work tasks. Our webbook features over 90 items of work across five units, with each item including a template of the standard method of measurement for quantity takeoff.

Standard Methods of Measurement for Quantity Takeoff: Topsoil Stripping, Stockpiling, and Placing

Work TaskTypical UOMPrimary Takeoff BasisDimensions RequiredStandard Formula / MethodAdjustment FactorsNotes & Visualization Guidance
PHASE 1: PRE-CONSTRUCTION & PLANNING
PREPARE, SUBMIT, AND OBTAIN APPROVALS FOR SPECIFIED SUBMITTALSLSTracking Log for SubmittalsSpecification Section Reference, Submittal Item CountSpecification Review and TrackingApproval cycles, resubmissionsFocus on the submittal schedule to ensure topsoil quality and erosion control material approvals do not delay field operations. Visualize the submittal workflow to identify potential bottlenecks early. Avoid missing requirements for soil testing certificates and organic content compliance during initial takeoff.
MOBILIZE AND SET UP AT LOCATIONLSLump Sum for MobilizationEquipment counts, site areaFixed costs + variable mobilization costsHaul distance, site accessMobilization includes equipment delivery, office setup, and temporary sediment control installation. Visualize the site layout to optimize topsoil stockpile and staging areas for productivity. Miscalculating site access requirements can significantly impact project workflow from Day 1.
PHASE 2: SITE PREPARATION & TOPSOIL STRIPPING
STRIP TOPSOIL TO SPECIFIED DEPTHCYVolumeStrip Area, Specified Stripping Depth, Existing Ground ElevationPlan Area × Specified Stripping Depth (Average End Area Method)Root mat density, stripping depth variance, existing vegetation coverMeasure stripping limits strictly within clearing and grubbing boundaries shown on cross-sections. Topsoil depth must be verified against geotechnical boring logs to separate organic layers from underlying subgrade clay or granular strata. A common mistake is measuring gross clearing area without factoring in localized depth variations.
DOZE & PUSH TOPSOIL TO STOCKPILE LOCATIONS ON SITECYVolumePush distance limits, Stockpile footprint area, Bank VolumeBank Volume = Stripped Plan Area × Average Stripping DepthSwell and shrink factors, haul grade slope, soil moisture conditionVerify that temporary stockpile footprints do not encroach on drainage swales, wetlands, or future structural foundation footprints. Quantities must reflect in-situ bank volume derived from cross-section end areas prior to displacement. Avoid ignoring storage easement limits or miscalculating bulking factors.
LOAD AND HAUL TOPSOIL TO STOCKPILE LOCATIONS ON SITECYVolumeBank Volume, Loose Volume, Haul Distance, Stockpile ElevationLoose Volume = Bank Volume × Swell Factor; Net Volume ReconciliationBank-to-loose swell factor, haul path grade resistance, material bulkingCalculate quantities by converting cut cross-section bank volume to loose volume using geotechnical swell factors. Verify haul path distances against site grading plans to prevent measuring across unauthorized terrain. Common takeoff errors involve failing to apply soil swell factors or neglecting shrink-swell adjustments.
PHASE 3: PLACEMENT, SPREADING & AMENDMENTS
PREPARE LOCATIONS TO RECEIVE TOPSOILSYAreaPlacement Surface Area, Perimeter Boundaries, Slope GradePlan Area Measurement (Length × Width or Coordinate Geometry)Subgrade scarification depth, compaction density requirements, moisture conditioningMeasure net surface areas where subgrade soils are designated for scarification to ensure proper bonding with topsoil layers. Verify slope limits and finished subgrade elevations against civil design cross-sections. A major takeoff error is measuring plan view flat area instead of actual sloping surface area.
LOAD AND HAUL TOPSOIL FROM STOCKPILE TO LOCATIONS INDICATEDCYVolumeCompacted Fill Volume, Stockpile Coordinates, Haul Distance, DepthBorrow Volume = Compacted Finish Volume ÷ Compaction Adjustment FactorCompaction shrinkage factor, stockpile moisture content, shrink-swell ratiosDetermine final placed volumes from cross-section profiles and apply appropriate shrinkage and compaction conversion factors. Verify finish grade contours against landscaping sheets to establish precise placement boundaries. Common errors include forgetting that stockpile material settles and bulks differently than in-situ bank soil.
ADD/BLEND SOIL AMENDMENTS AS NECESSARYSYAreaTreatment Surface Area, Application Rate (lbs/SY or tons/acre), Incorporation DepthPlan Area Measurement × Specification Application RateSoil test fertilizer requirements, moisture content, tilling depth, dispersion efficiencyMeasure treatment areas strictly across designated turf establishment and slope stabilization zones per specification sheets. Verify application rates against agronomist soil test recommendations rather than generic design assumptions. A frequent takeoff error is assuming uniform amendment rates across variable soil types.
SPREAD AND PLACE TOPSOIL AT LOCATIONS INDICATEDCY, SYVolumePlacement Area, Finished Depth, Subgrade Elevation, Proposed Grade ElevationVolume = Plan Area × Specified Loose Depth; Area = Plan Area MeasurementCompaction settlement allowance, loose-to-compacted shrinkage factor, tolerance limitsMeasure surface area in square yards and corresponding loose volume in cubic yards based on specified layer thickness (typically 4 to 6 inches). Verify final topsoil elevation tolerances against civil grading sheets to ensure positive runoff and prevent ponding. Common takeoff errors include failing to account for settlement compaction.
PHASE 4: SITE CLOSEOUT & EXCESS MANAGEMENT
LOAD AND HAUL OFF EXCESS TOPSOILCYVolumeExcess Stockpile Volume, Haul Distance, Disposal Site DimensionsNet Excess Volume = Total Stripped Bank Volume − Total Placed Fill VolumeSwell factor, disposal site permit limits, haul route restrictionsCalculate surplus material remaining in temporary stockpiles after site grading and landscaping operations are complete by balancing cut and fill volumes. Verify disposal site boundaries and permit restrictions prior to finalizing quantity takeoffs. A common takeoff error is neglecting haul route restrictions and disposal tipping fee boundaries.
DEMOBILIZE AND MOVE OUT OF SITELSLump Sum for DemobilizationFacility Square Footage, Site Restoration Area, Punch List Item CountLump Sum Percentage Allocation & Area Measurement MethodSite clean-up requirements, environmental remediation, final inspection punch listVerify that all temporary erosion controls and staging areas slated for restoration are measured against original condition surveys and environmental permits. Confirm site restoration boundaries match contract closeout specifications. Common takeoff errors include omitting final site cleanup, seedbed repair of staging yards, and environmental closure documentation.