Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: East River Bridge Rehabilitation
Location: New York, New York
Year: 2016
Project Size: $520 million
Scope: Structural repairs and upgrades to a major urban bridge, including utility relocations
Lead Agencies/Contractors: New York City Department of Transportation /


Category of the Issue, Problem, or Challenge
• Utility Relocation
• Project Delay


Summary of the Issue, Problem, or Challenge
Unexpected underground utilities required relocation, causing significant construction delays.


Root Cause Analysis

  • Incomplete Utility Mapping: Existing records were outdated or inaccurate.
  • Coordination Failures: Poor communication between utility companies and construction team.
  • Permitting Delays: Utility relocation permits took longer than expected.
  • Construction Sequencing: Delays in utility work cascaded to other construction activities.

Impacts Due to the Issue, Problem, or Challenge

  • Project delayed by 9 months.
  • Increased costs from extended mobilization and overhead.
  • Stakeholder frustration due to prolonged disruptions.

Corrective Actions Taken

  1. Updated utility mapping with advanced detection technologies pre-construction.
  2. Established dedicated utility coordination teams.
  3. Accelerated permitting processes through early engagement with agencies.
  4. Revised construction sequencing to minimize dependency on utilities.

Lessons Learned

  • Accurate utility data is critical for planning.
  • Early and continuous utility coordination reduces delays.
  • Flexible sequencing mitigates impact of utility-related issues.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has utility mapping been thoroughly verified?
  • Are utility companies engaged early and frequently?
  • Is construction sequencing flexible to accommodate utility delays?