Project Overview
• Name: Ohio River Bridge Replacement
• Location: Ohio/Kentucky Border
• Year: 2014
• Project Size: $750 million
• Scope: Construction of a new major highway bridge over the Ohio River
• Lead Agencies/Contractors: Ohio Department of Transportation (ODOT), Kentucky Transportation Cabinet /


Category of the Issue, Problem, or Challenge
• Material Supply
• Project Delay


Summary of the Issue, Problem, or Challenge
Shortages of structural steel delayed key fabrication and erection phases.


Root Cause Analysis

  • Global Steel Market Volatility: Price spikes and limited supply affected procurement.
  • Single Supplier Reliance: Limited vendor options delayed orders.
  • Contractual Timing: Late procurement contracts without buffer stock.
  • Lack of Alternative Material Planning: No contingency sourcing plans were in place.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 6 months.
  • Increased costs from expedited freight and premium pricing.
  • Impact on contractor cash flow and scheduling.

Corrective Actions Taken

  1. Diversified steel suppliers and developed long-term procurement contracts.
  2. Incorporated material market risk analysis in planning.
  3. Created on-site buffer stock for critical materials.
  4. Monitored global market trends to anticipate disruptions.

Lessons Learned

  • Material market conditions can critically impact schedule.
  • Proactive procurement and supplier diversification mitigate risk.
  • Buffer inventories protect against supply chain shocks.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are supplier markets monitored and alternative sources identified?
  • Is there on-site inventory for critical materials?
  • Are procurement contracts timed to account for market volatility?