Project Overview
• Name: Miami Port Expansion
• Location: Miami, Florida
• Year: 2018
• Project Size: $350 million
• Scope: Port terminal expansion with dredging and marine construction
• Lead Agencies/Contractors: Florida DOT /


Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Environmental Compliance


Summary of the Issue, Problem, or Challenge
Marine subcontractor failed to comply with environmental permit conditions during dredging, leading to sediment spills and a regulatory stop-work order.


Root Cause Analysis

  • Lack of subcontractor environmental training and awareness.
  • Inadequate supervision and monitoring of subcontractor activities by prime contractor.
  • Failure to implement required sediment control measures.
  • Poor communication between subcontractor and environmental inspectors.

Impacts Due to the Issue, Problem, or Challenge

  • Work suspended for 6 weeks to address violations and implement corrective measures.
  • Increased costs due to mitigation efforts, fines, and schedule impact.
  • Reputational damage and strained relations with regulatory agencies.

Corrective Actions Taken

  1. Subcontractor conducted mandatory environmental compliance training.
  2. Prime contractor increased on-site environmental supervision.
  3. Implemented enhanced sediment and erosion control plans.
  4. Established regular communication protocols with regulators.

Lessons Learned

  • Subcontractors must be fully trained on environmental requirements.
  • Continuous monitoring is necessary to prevent compliance breaches.
  • Early communication with regulators can mitigate risk of stop-work orders.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are subcontractors trained and certified on environmental compliance?
  • How is subcontractor environmental performance monitored?
  • Are sediment and erosion controls regularly inspected and maintained?