Project Overview
• Name: I-15 Widening Project
• Location: Las Vegas, Nevada
• Year: 2018
• Project Size: $340 million
• Scope: Highway widening with significant earthwork and excavation
• Lead Agencies/Contractors: Nevada DOT /


Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Equipment Reliability


Summary of the Issue, Problem, or Challenge
Excavation subcontractor’s heavy machinery experienced repeated breakdowns due to inadequate maintenance, causing significant delays in earthmoving operations.


Root Cause Analysis

  • Poor maintenance schedules and recordkeeping by subcontractor.
  • Use of outdated or overworked equipment.
  • Insufficient spare parts inventory and delayed repair response.
  • Lack of prime contractor oversight on subcontractor equipment condition.

Impacts Due to the Issue, Problem, or Challenge

  • 4-week delay in excavation and grading phases.
  • Increased costs due to rental of replacement equipment and overtime labor.
  • Cascading effects on subsequent construction activities.

Corrective Actions Taken

  1. Subcontractor implemented rigorous preventive maintenance programs.
  2. Prime contractor required equipment inspections before mobilization.
  3. Established quick-response repair teams and spare parts inventory.
  4. Regular equipment condition reporting to prime contractor.

Lessons Learned

  • Equipment reliability is critical for maintaining schedule in heavy earthwork.
  • Preventive maintenance and proactive oversight reduce downtime.
  • Clear reporting mechanisms between subcontractor and prime contractor improve equipment management.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are subcontractor equipment maintenance schedules documented and followed?
  • Is equipment inspected regularly before deployment?
  • Are rapid repair and spare parts systems in place?