Case Study: Delay from Site Conditions on Denver Airport Expansion (Denver, CO, 2015)
Project Overview
• Name: Denver International Airport Expansion
• Location: Denver, Colorado
• Year: 2015
• Project Size: $1.2 billion
• Scope: Terminal expansion and runway improvements
• Lead Agencies/Contractors: Denver Airport Authority /
Category of the Issue, Problem, or Challenge
• Site Conditions
• Project Delay
Summary of the Issue, Problem, or Challenge
Unexpected poor soil conditions and high groundwater levels caused delays in foundation work and dewatering operations.
Root Cause Analysis
- Incomplete Geotechnical Data: Soil borings were insufficiently detailed or not representative.
- Underestimation of Groundwater Impacts: Dewatering requirements were more extensive than planned.
- Design Adjustments: Foundation designs had to be revised mid-construction.
- Procurement Delays: Specialized equipment for dewatering arrived late.
Impacts Due to the Issue, Problem, or Challenge
- Delay of 8 months.
- Increased costs for additional foundation works and dewatering.
- Contractor claims and schedule disputes.
Corrective Actions Taken
- Increased geotechnical investigations for future phases.
- Developed robust groundwater management plans.
- Allowed flexible design adaptation and fast-track approvals.
- Improved procurement planning for specialized equipment.
Lessons Learned
- Thorough site investigation prevents unexpected conditions.
- Groundwater management is critical for underground work.
- Flexibility and rapid response reduce delay impacts.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are geotechnical surveys comprehensive and current?
- Is groundwater impact assessed and mitigated?
- Are designs adaptable to changing site conditions?