Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Denver International Airport Expansion
Location: Denver, Colorado
Year: 2015
Project Size: $1.2 billion
Scope: Terminal expansion and runway improvements
Lead Agencies/Contractors: Denver Airport Authority /


Category of the Issue, Problem, or Challenge
• Site Conditions
• Project Delay


Summary of the Issue, Problem, or Challenge
Unexpected poor soil conditions and high groundwater levels caused delays in foundation work and dewatering operations.


Root Cause Analysis

  • Incomplete Geotechnical Data: Soil borings were insufficiently detailed or not representative.
  • Underestimation of Groundwater Impacts: Dewatering requirements were more extensive than planned.
  • Design Adjustments: Foundation designs had to be revised mid-construction.
  • Procurement Delays: Specialized equipment for dewatering arrived late.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 8 months.
  • Increased costs for additional foundation works and dewatering.
  • Contractor claims and schedule disputes.

Corrective Actions Taken

  1. Increased geotechnical investigations for future phases.
  2. Developed robust groundwater management plans.
  3. Allowed flexible design adaptation and fast-track approvals.
  4. Improved procurement planning for specialized equipment.

Lessons Learned

  • Thorough site investigation prevents unexpected conditions.
  • Groundwater management is critical for underground work.
  • Flexibility and rapid response reduce delay impacts.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are geotechnical surveys comprehensive and current?
  • Is groundwater impact assessed and mitigated?
  • Are designs adaptable to changing site conditions?