Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-70 Mountain Corridor Expansion
Location: Colorado
Year: 2017
Project Size: $400 million
Scope: Road widening and safety improvements through mountainous terrain
Lead Agencies/Contractors: Colorado Department of Transportation (CDOT) /


Category of the Issue, Problem, or Challenge
• Environmental / Archaeological
• Project Delay


Summary of the Issue, Problem, or Challenge
Construction was halted for several months following discovery of significant archaeological artifacts requiring careful excavation and regulatory review.


Root Cause Analysis

  • Insufficient Pre-Construction Surveys: Archaeological investigations were limited prior to construction start.
  • Regulatory Compliance: Federal laws required stopping work for artifact protection.
  • Coordination Delays: Archaeologists and contractors had limited prior integration in planning.
  • Scheduling Inflexibility: Project timeline did not account for potential archaeological work.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 4 months.
  • Increased costs due to archaeological investigations and work stoppages.
  • Rescheduling impacts on subsequent construction phases.

Corrective Actions Taken

  1. Expanded archaeological surveys for future projects before ground-breaking.
  2. Integrated archaeologists into early planning and scheduling.
  3. Developed contingency plans for unanticipated finds.
  4. Improved training for site personnel to recognize potential artifacts.

Lessons Learned

  • Thorough cultural resource surveys reduce construction interruptions.
  • Early involvement of archaeologists improves coordination.
  • Project schedules must include contingencies for environmental and cultural compliance.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are archaeological and cultural resource assessments complete and up-to-date?
  • Is there a plan to quickly address unexpected findings?
  • Are personnel trained to recognize and report artifacts?