Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Houston I-45 Freeway Expansion
Location: Houston, Texas
Year: 2016
Project Size: $1.1 billion
Scope: Expansion of freeway lanes and interchange improvements
Lead Agencies/Contractors: Texas Department of Transportation (TxDOT) /


Category of the Issue, Problem, or Challenge
• Traffic Management
• Project Delay


Summary of the Issue, Problem, or Challenge
Poorly planned traffic detours and lane closures led to severe congestion, public backlash, and forced construction pauses to revise traffic plans.


Root Cause Analysis

  • Insufficient Traffic Impact Analysis: Detours underestimated peak congestion.
  • Lack of Stakeholder Engagement: Limited input from local authorities and community.
  • Communication Failures: Poor dissemination of traffic changes to the public.
  • Rigid Construction Sequencing: Inability to adjust lane closures dynamically.

Impacts Due to the Issue, Problem, or Challenge

  • Construction delays totaling 4 months.
  • Increased costs from revised traffic management and extended work hours.
  • Negative public relations and political pressure.

Corrective Actions Taken

  1. Re-evaluated traffic management plans with detailed modeling.
  2. Increased stakeholder collaboration for detour planning.
  3. Enhanced public communication and real-time updates.
  4. Introduced flexible lane closure strategies.

Lessons Learned

  • Comprehensive traffic planning reduces construction impact.
  • Community and authority engagement improves acceptance.
  • Dynamic traffic management adapts better to evolving conditions.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are traffic impacts fully modeled and mitigated?
  • Are stakeholders consulted and communication plans robust?
  • Is traffic management flexible and responsive during construction?