Case Study: QC Deficiencies in Concrete Formwork on Chicago Riverwalk Extension (Illinois, 2017)
Project Overview
• Name: Chicago Riverwalk Expansion
• Location: Chicago, Illinois
• Year: 2017
• Project Size: $150 million
• Scope: Concrete formwork and structural pours along the riverwalk
• Lead Agencies/Contractors: City of Chicago /
Category of the Issue, Problem, or Challenge
• Quality Control
• Structural
Summary of the Issue, Problem, or Challenge
Formwork failures and misalignment caused surface defects and structural inconsistencies, requiring partial demolition and rework.
Root Cause Analysis
- Poor inspection of formwork alignment and integrity before pours.
- Insufficient training for formwork carpenters and QC inspectors.
- Lack of standardized formwork erection and inspection checklists.
- Inadequate communication between formwork and concrete placement teams.
Impacts Due to the Issue, Problem, or Challenge
- Delay of 2 months due to demolition and re-pour.
- Increased costs for labor, materials, and schedule extension.
- Potential long-term durability risks from formwork defects.
Corrective Actions Taken
- Developed detailed formwork erection and inspection checklists.
- Conducted training for formwork crews and QC inspectors.
- Enhanced communication protocols between formwork and concrete teams.
- Increased QC inspections prior to concrete placement.
Lessons Learned
- Proper formwork inspection prevents costly defects.
- Training and standardized procedures improve quality.
- Coordination between crews is key for seamless pours.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are formwork structures inspected and approved before pouring?
- Are formwork crews and inspectors adequately trained?
- Is communication maintained between formwork and concrete teams?