Case Study: Subcontractor Schedule Mismanagement Causes Utility Relocation Delay in California (2019)
Project Overview
• Name: I-405 Improvement Project
• Location: Los Angeles, California
• Year: 2019
• Project Size: $450 million
• Scope: Freeway widening, including complex utility relocations
• Lead Agencies/Contractors: California DOT /
Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Schedule & Coordination
Summary of the Issue, Problem, or Challenge
Utility subcontractors fell behind schedule due to poor planning and resource allocation, delaying subsequent roadway paving and widening activities.
Root Cause Analysis
- Subcontractors underestimated scope and complexity of utility work.
- Inadequate coordination meetings and communication between prime and subs.
- Lack of contingency plans for unforeseen utility conflicts.
- Poor subcontractor resource management and schedule adherence.
Impacts Due to the Issue, Problem, or Challenge
- Overall project delay of 3 months, with cascading impacts on critical path.
- Increased project costs from extended overhead and re-mobilization.
- Stakeholder dissatisfaction and negative public perception.
Corrective Actions Taken
- Prime contractor improved subcontractor coordination through weekly progress meetings.
- Developed detailed work sequencing and contingency plans for utilities.
- Instituted stricter progress reporting and performance reviews for subs.
- Allocated additional resources and support to subcontractors facing delays.
Lessons Learned
- Utility work requires thorough upfront planning and flexible scheduling.
- Continuous communication between prime and subs prevents misunderstandings.
- Subcontractor performance must be closely monitored against critical path.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are subcontractor schedules integrated into overall project plan?
- How often are coordination and progress meetings held?
- Are contingency plans established for utility conflicts?