Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-95 Reconstruction
Location: Philadelphia, Pennsylvania
Year: 2017
Project Size: $1 billion
Scope: Interstate reconstruction including major concrete work
Lead Agencies/Contractors: Pennsylvania DOT /


Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Scheduling & Coordination


Summary of the Issue, Problem, or Challenge
Concrete subcontractor’s failure to coordinate delivery schedules with prime contractor and suppliers caused multiple delays and inefficient pour sequencing.


Root Cause Analysis

  • Subcontractor’s internal scheduling processes were inadequate and reactive.
  • Lack of integrated project scheduling tools shared with prime contractor.
  • Poor communication between subcontractor, concrete suppliers, and site teams.
  • No penalties or incentives tied to schedule adherence.

Impacts Due to the Issue, Problem, or Challenge

  • Multiple days of lost work due to delayed material arrival.
  • Increased costs from labor inefficiencies and extended site overhead.
  • Negative impact on overall project critical path and stakeholder confidence.

Corrective Actions Taken

  1. Implemented shared digital scheduling tools for all parties.
  2. Established weekly coordination meetings between subcontractor, prime, and suppliers.
  3. Added schedule adherence clauses with financial incentives and penalties.
  4. Trained subcontractor staff on proactive scheduling and communication.

Lessons Learned

  • Scheduling coordination is critical for heavy civil concrete operations.
  • Digital tools and frequent communication reduce risks of delays.
  • Contractual provisions improve accountability for schedule adherence.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are subcontractor schedules integrated with overall project plans?
  • Are communication protocols and coordination meetings regular and documented?
  • Are schedule-related contractual incentives and penalties clearly defined?