Case Study: Subcontractor Delay in Steel Fabrication Impacts Bridge Construction in Washington State (2019)
Project Overview
• Name: Tacoma Narrows Bridge Expansion
• Location: Tacoma, Washington
• Year: 2019
• Project Size: $580 million
• Scope: Bridge widening with major steel components
• Lead Agencies/Contractors: Washington DOT /
Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Scheduling & Supply Chain
Summary of the Issue, Problem, or Challenge
The steel fabrication subcontractor missed critical delivery dates due to production bottlenecks and material shortages, causing a 5-week delay in bridge erection.
Root Cause Analysis
- Insufficient capacity planning and scheduling by subcontractor.
- Delays in steel supply due to vendor issues.
- Poor communication between subcontractor and prime contractor.
- Lack of contingency planning for production disruptions.
Impacts Due to the Issue, Problem, or Challenge
- Schedule slippage impacting overall project timeline.
- Increased labor and equipment rental costs.
- Contractual disputes and penalty exposure.
Corrective Actions Taken
- Revised production scheduling and capacity planning.
- Diversified steel suppliers to reduce material risk.
- Improved communication protocols and progress reporting.
- Developed contingency plans for supply chain disruptions.
Lessons Learned
- Accurate production and supply planning prevent delays.
- Strong supplier relationships reduce material risks.
- Transparent communication between all parties is essential.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are subcontractor fabrication schedules realistic and monitored?
- Are material suppliers vetted and alternatives prepared?
- Is communication proactive and frequent?