Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-76 Slope Stabilization & Retaining Walls
Location: Pittsburgh, Pennsylvania
Year: 2021
Project Size: $145 million
Scope: Roadside slope stabilization and retaining wall reconstruction
Lead Agencies/Contractors: Pennsylvania DOT (Owner) /


Category of the Issue, Problem, or Challenge
• Contract Owner
• Mid-Construction Design Changes


Summary of the Issue, Problem, or Challenge
PennDOT issued a mid-construction directive to redesign 2 retaining walls based on new geotechnical studies, pausing fieldwork for 10 weeks while engineering and permits were revised.


Root Cause Analysis

  • Owner authorized early construction start before full geotechnical review.
  • Site conditions revealed wall foundation risks not accounted for in original design.
  • Design changes required revised calculations, drawings, and re-permitting.

Impacts Due to the Issue, Problem, or Challenge

  • Construction halted for redesign, delaying adjacent earthworks.
  • Cost increase of $7.3 million due to new foundation materials.
  • Contractual dispute over cost liability for owner-initiated changes.

Corrective Actions Taken

  1. PennDOT restructured design review workflows to delay NTP until final investigations.
  2. Geotechnical peer reviews were added prior to releasing construction packages.
  3. Contingency fund for owner-driven changes was added to future contracts.

Lessons Learned

  • Owners must complete all critical investigations before issuing NTP.
  • Midstream design changes impact schedule, cost, and contractor trust.
  • Shared risk provisions help mitigate redesign disruption.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are site conditions and design packages fully validated pre-construction?
  • Does the contract define liability for owner-initiated design revisions?
  • Is there a pre-established process for rapid redesign and approval?