Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: SR 99 Tunnel North Portal Approach Structures
Location: Seattle, Washington
Year: 2016
Project Size: $85 million (portion of $3.3B Alaskan Way Viaduct Replacement)
Scope: Approach structures, retaining walls, and ramp construction for tunnel access
Lead Agencies/Contractors: WSDOT /


Category of the Issue, Problem, or Challenge
• Labor Dispute
• Industrial Relations


Summary of the Issue, Problem, or Challenge
Ironworkers and pile drivers initiated a strike over local union jurisdictional disputes, halting steel erection and piling activities for nearly a month. Mediation was delayed due to overlapping negotiations with a separate tunneling workforce.


Root Cause Analysis

FactorDetails
Jurisdictional ConflictDispute over whether steel assembly tasks fell under ironworker or laborer scope
Owner’s RoleWSDOT remained neutral, delaying dispute resolution
Contract LanguageVague scope definition allowed overlapping claims
Delayed MediationNo pre-arranged labor dispute protocol in place

Impacts Due to the Issue, Problem, or Challenge
• 28-day work stoppage on critical path structures
• Idle equipment and standby labor costs exceeded $1.1 million
• Construction resequencing led to cost and coordination impacts in adjacent work zones


Corrective Actions Taken

  1. Union jurisdiction clarified for future scopes via pre-job conferences
  2. Labor dispute escalation procedure added to future contract boilerplate
  3. WSDOT created a labor liaison officer position for major urban projects

Lessons Learned
• Jurisdictional clarity must be established early with unions on multi-trade scopes
• Public owners should prepare for active facilitation of labor disputes
• Schedule buffers are needed when multiple high-stakes trades overlap


Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Have pre-job union jurisdictional agreements been documented?
  • Is there a labor dispute resolution pathway embedded in the contract?
  • Are labor disruptions modeled into the project risk register?