Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Denver I-70 East Viaduct Replacement
Location: Denver, Colorado
Year: 2020
Project Size: $1.2 billion
Scope: Replacement of aging highway viaduct with new elevated structures
Lead Agencies/Contractors: Colorado DOT, Design-Build Contractor


Category of the Issue, Problem, or Challenge
• Design
• Structural Engineering


Summary of the Issue, Problem, or Challenge
During construction, discrepancies between design specifications and field conditions resulted in significant rework of structural elements. Design flaws included underestimation of foundation load requirements and insufficient detailing for seismic resistance, requiring redesign and delay.


Root Cause Analysis

  • Inadequate geotechnical data integration into foundation design.
  • Insufficient seismic load consideration in structural calculations.
  • Lack of constructability review led to design details not aligning with field realities.
  • Communication gaps between design engineers and field teams.

Impacts Due to the Issue, Problem, or Challenge
• 6-month project delay due to redesign and rework.
• Cost overruns estimated at $8 million.
• Increased safety and quality assurance scrutiny.


Corrective Actions Taken

  1. Conducted detailed geotechnical reassessment and updated foundation designs.
  2. Revised structural models to incorporate seismic loads per updated codes.
  3. Instituted cross-disciplinary constructability reviews during design phase.
  4. Enhanced coordination protocols between design and construction teams.

Lessons Learned

  • Comprehensive site data must be fully integrated into design early on.
  • Seismic and other environmental loads require rigorous assessment and updating.
  • Constructability reviews prevent costly on-site design conflicts.
  • Strong communication between design and field teams is critical.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are site conditions fully captured and incorporated in design?
  • Have seismic and environmental factors been rigorously evaluated?
  • Is there a formal constructability review involving construction input?
  • Are design changes promptly communicated to all stakeholders?