Project Overview
Name: I-70 Mountain Corridor Reconstruction
Location: Colorado
Year: 2010
Project Size: $1.2 billion
Scope: Reconstruction of mountainous highway section with tunnels, bridges, and retaining walls
Lead Agencies/Contractors: Colorado Department of Transportation (CDOT) /


Category of the Issue, Problem, or Challenge
• Design Errors
• Cost Management


Summary of the Issue, Problem, or Challenge
Design errors in retaining wall specifications led to structural modifications and costly rework during construction.


Root Cause Analysis

  • Insufficient Geotechnical Data: Underestimation of rock and soil pressures on retaining walls.
  • Design Miscalculations: Structural designs did not meet required load factors.
  • Lack of Peer Review: Designs were not subjected to rigorous third-party reviews.
  • Change Management: Slow response to identified errors delayed corrective actions.

Impacts Due to the Issue, Problem, or Challenge

  • Cost overruns of approximately 17% due to rework and additional materials.
  • Construction delays of nearly five months.
  • Increased risk and liability concerns.

Corrective Actions Taken

  1. Conducted thorough peer reviews of all structural designs.
  2. Enhanced geotechnical investigation protocols.
  3. Implemented rapid response teams for design error detection and correction.
  4. Instituted stronger quality control and design verification processes.

Lessons Learned

  • Comprehensive design verification reduces costly construction-phase corrections.
  • Accurate geotechnical data is crucial for mountain infrastructure projects.
  • Early peer reviews help catch errors before construction starts.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are designs peer-reviewed and quality-checked before construction?
  • Is geotechnical data comprehensive and recent?
  • Are processes in place for swift response to design errors?