Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: North Houston Highway Improvement Project (NHHIP)
Location: Houston, Texas
Year: 2019
Project Size: $7 billion (phase-wise)
Scope: Widening and reconstruction of I-45 corridor using a phased Design-Build approach
Lead Agencies/Contractors: Texas DOT, Design-Build Contractor JV


Category of the Issue, Problem, or Challenge
• Project Delivery Method
• Design-Build


Summary of the Issue, Problem, or Challenge
Significant disputes arose between owner and contractor over unforeseen site conditions and schedule pressures. Contract ambiguities over risk-sharing and scope changes led to multiple change orders and slowed construction progress.


Root Cause Analysis

  • Contractual risk allocation unclear for subsurface conditions.
  • Inadequate geotechnical investigations before construction.
  • Aggressive schedule unrealistic for scope complexity.
  • Lack of early collaboration on scope modifications.

Impacts Due to the Issue, Problem, or Challenge
• Construction delays exceeding 9 months.
• Cost overruns of approximately $150 million.
• Increased adversarial contract management environment.


Corrective Actions Taken

  1. Contract amendments clarifying risk sharing on site conditions.
  2. Enhanced subsurface investigation program for subsequent phases.
  3. Joint scheduling workshops to establish realistic timelines.
  4. Improved collaboration forums for scope and design changes.

Lessons Learned

  • Clear risk allocation for site conditions is critical in Design-Build contracts.
  • Thorough pre-construction investigations reduce surprises.
  • Realistic scheduling reduces pressure-induced conflicts.
  • Collaboration improves management of evolving project scope.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are site condition risks clearly allocated?
  • Are geotechnical investigations adequate and timely?
  • Is schedule development realistic and collaborative?
  • Are change management processes well defined and cooperative?