Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-95 Express Lanes Extension
Location: Miami, Florida
Year: 2017
Project Size: $615 million
Scope: Extension of tolled express lanes using a Design-Build delivery approach
Lead Agencies/Contractors: Florida Department of Transportation (FDOT), Design-Build Contractor JV


Category of the Issue, Problem, or Challenge
• Project Delivery Method
• Design-Build


Summary of the Issue, Problem, or Challenge
During construction, unresolved scope changes and ambiguous contract terms regarding utility relocations caused delays and disputes. The fast-track Design-Build schedule intensified coordination challenges, leading to rework and increased costs.


Root Cause Analysis

  • Insufficient early utility coordination and mapping.
  • Ambiguity in contract terms concerning utility relocation responsibilities.
  • Fast-track schedule limited time for design refinements.
  • Inadequate risk sharing provisions for unforeseen utility conflicts.

Impacts Due to the Issue, Problem, or Challenge
• Schedule delays of 5 months.
• Cost overruns of approximately $30 million.
• Increased contractual disputes requiring mediation.


Corrective Actions Taken

  1. Clarified contract language on utility responsibilities in change orders.
  2. Implemented early utility coordination meetings with stakeholders.
  3. Added contingency time buffers for utility relocation in schedule updates.
  4. Enhanced risk management workshops focusing on utility-related risks.

Lessons Learned

  • Early and thorough utility investigations are essential in Design-Build projects.
  • Clear contract provisions for utility relocations reduce disputes.
  • Fast-track schedules must balance speed with realistic design and coordination time.
  • Collaborative risk management improves issue resolution.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are utility responsibilities clearly defined contractually?
  • Has early utility coordination been performed?
  • Is schedule realistic given utility relocation needs?
  • Are risk sharing provisions adequate for utility conflicts?