Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Central Subway Project
Location: San Francisco, California
Year: 2018
Project Size: $1.6 billion
Scope: 1.7-mile light rail tunnel with underground stations
Lead Agencies/Contractors: San Francisco Municipal Transportation Agency (SFMTA) /


Category of the Issue, Problem, or Challenge
• Contract Change Order
• MEP Coordination


Summary of the Issue, Problem, or Challenge
Mechanical, electrical, and plumbing (MEP) systems required extensive rework after field crews identified major spatial conflicts with structural and architectural components. These coordination issues resulted in substantial change orders, primarily due to insufficient integration of MEP during design and lack of clash detection before fabrication.


Root Cause Analysis

  • Incomplete design at bid stage
  • Inadequate use of BIM for coordination
  • Accelerated procurement of materials before design finalization
  • Field conditions differed from as-built assumptions in drawings

Impacts Due to the Issue, Problem, or Challenge
• Over $90 million in change orders
• Delays to station fit-out and systems integration
• Increased tension between contractor and agency leadership


Corrective Actions Taken

  1. Required use of federated BIM models for all underground station work
  2. Instituted “no fabrication without coordination” policy
  3. Added constructability reviews by third-party MEP consultants
  4. Contract modifications to share risk of design-driven rework

Lessons Learned

  • Full MEP coordination must precede procurement and field work
  • BIM is only effective if all trades and disciplines are fully engaged
  • Change orders from uncoordinated systems create long-term cost and time impacts
  • Schedule compression cannot justify skipping coordination milestones

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has full MEP coordination been completed before issuing for construction?
  • Are BIM clash reports reviewed and resolved prior to fabrication?
  • Is there a dedicated MEP lead managing cross-discipline integration?
  • Are contract terms clear about responsibility for uncoordinated designs?