Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Chicago Deep Tunnel System Rehab
Location: Chicago, Illinois
Year: 2021
Project Size: $530 million
Scope: Structural rehabilitation and waterproofing of deep tunnel infrastructure
Lead Agencies/Contractors: Chicago DOT /


Category of the Issue, Problem, or Challenge
• Supply Chain Disruption
• Chemical Admixtures for Concrete


Summary of the Issue, Problem, or Challenge
The project encountered delays when key chemical admixtures (water reducers and corrosion inhibitors) were backordered due to global supply constraints in specialty chemicals.


Root Cause Analysis

  • Global shortages in petrochemical raw materials needed for admixture production.
  • Increased demand from concurrent construction and industrial sectors.
  • Limited number of admixture manufacturers qualified for high-spec tunnel concrete.
  • Lack of alternate admixture suppliers and contingency procurement plans.

Impacts Due to the Issue, Problem, or Challenge
• 2.5-month delay in concrete placement and curing schedules.
• Additional costs for expedited shipments and admixture substitutions (~$2.4 million).
• Risk of compromised concrete performance and project quality control.


Corrective Actions Taken

  1. Identified and qualified alternative admixture suppliers.
  2. Modified mix designs to reduce reliance on scarce admixtures.
  3. Established advanced procurement and supply monitoring systems.

Lessons Learned

  • Specialty chemical supply chains can pose significant project risks.
  • Flexibility in material specifications helps mitigate supply disruptions.
  • Early qualification of multiple suppliers reduces schedule impacts.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are admixture suppliers diversified and pre-qualified?
  • Is procurement timing sufficient for specialty materials?
  • Are mix designs adaptable to changes in admixture availability?