Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Philadelphia Tunnel Rehabilitation
Location: Philadelphia, Pennsylvania
Year: 2021
Project Size: $370 million
Scope: Tunnel lining and concrete repairs
Lead Agencies/Contractors: Pennsylvania DOT /


Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Quality Control – Concrete


Summary of the Issue, Problem, or Challenge
Concrete subcontractor’s poor mixing and placement practices resulted in areas of honeycombing and low strength, necessitating costly repairs and delaying the tunnel rehabilitation.


Root Cause Analysis

  • Inadequate batching and mixing controls.
  • Insufficient supervision during concrete placement.
  • Lack of proper curing and finishing procedures.
  • Ineffective QC inspections and testing.

Impacts Due to the Issue, Problem, or Challenge

  • Rework and repair of defective concrete sections.
  • Schedule extension of 7 weeks.
  • Increased labor and material expenses.
  • Risk of compromised structural integrity if uncorrected.

Corrective Actions Taken

  1. Enforced strict batching and mixing standards.
  2. Increased onsite supervision during placement.
  3. Improved curing and finishing protocols.
  4. Enhanced QC testing and documentation procedures.

Lessons Learned

  • Proper concrete mixing and placement are vital for structural performance.
  • Continuous supervision and testing catch defects early.
  • Subcontractor QC must align closely with prime contractor requirements.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are concrete batching and placement procedures strictly followed?
  • Is onsite supervision adequate during critical operations?
  • Are QC inspections frequent and well documented?