Case Study: Cost Overrun Due to Construction Delay on Pennsylvania Bridge Replacement (Pittsburgh, PA, 2014)
Project Overview
• Name: Pittsburgh Bridge Replacement Project
• Location: Pittsburgh, Pennsylvania
• Year: 2014
• Project Size: $350 million
• Scope: Replacement of aging steel bridge with modern multi-span structure
• Lead Agencies/Contractors: Pennsylvania Department of Transportation (PennDOT) /
Category of the Issue, Problem, or Challenge
• Construction Delay
• Cost Management
Summary of the Issue, Problem, or Challenge
Extended construction delays due to contractor performance issues and weather interruptions led to substantial cost overruns.
Root Cause Analysis
- Contractor Resource Shortages: Inadequate labor and equipment availability slowed progress.
- Adverse Weather: Prolonged wet conditions reduced work days and productivity.
- Inadequate Scheduling: Ineffective schedule management and failure to mitigate delays.
- Communication Breakdowns: Delayed decision-making and issue resolution.
Impacts Due to the Issue, Problem, or Challenge
- Cost overruns estimated at 20%.
- Project completion delayed by nearly eight months.
- Increased liquidated damages risk and stakeholder dissatisfaction.
Corrective Actions Taken
- Imposed stricter contractor performance monitoring and penalties.
- Developed detailed weather contingency and recovery plans.
- Enhanced project schedule controls with regular progress assessments.
- Improved communication protocols and escalation procedures.
Lessons Learned
- Contractor resource planning is critical to meet schedules.
- Weather impacts require robust mitigation strategies.
- Strong project controls and communication reduce delay risks.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are contractor resources sufficient and monitored?
- Are weather risks accounted for in scheduling?
- Are communication and escalation protocols effective?