Case Study: Cost Overrun from Change Orders on Seattle Alaskan Way Viaduct Replacement Tunnel (Seattle, WA, 2013)
Project Overview
• Name: Alaskan Way Viaduct Replacement Tunnel
• Location: Seattle, Washington
• Year: 2013
• Project Size: $3.3 billion
• Scope: Construction of a deep-bore tunnel to replace an aging elevated highway viaduct
• Lead Agencies/Contractors: Washington State Department of Transportation (WSDOT) /
Category of the Issue, Problem, or Challenge
• Change Orders
• Cost Management
Summary of the Issue, Problem, or Challenge
Numerous change orders due to unforeseen underground conditions and design modifications led to significant cost escalations.
Root Cause Analysis
- Unforeseen Subsurface Conditions: Variable soil and groundwater conditions necessitated design and method changes.
- Design Modifications: Changes requested by stakeholders and regulatory agencies during construction.
- Contractor Claims: Additional costs claimed for extra work and delays.
- Scope Creep: Expansion of project scope beyond initial design without early cost reconciliation.
Impacts Due to the Issue, Problem, or Challenge
- Cost overruns estimated at 15-20% beyond original contract value.
- Construction delays impacting overall transportation network.
- Heightened scrutiny by public and governmental oversight bodies.
Corrective Actions Taken
- Strengthened change order management processes with clear approval workflows.
- Improved subsurface investigation methods for future projects.
- Enhanced stakeholder communication to manage scope changes proactively.
- Increased contingency budgets for change orders.
Lessons Learned
- Effective change order management is critical to controlling costs.
- Early and thorough subsurface investigations reduce unexpected changes.
- Clear communication with stakeholders helps manage scope and cost expectations.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are change orders tracked and approved with rigorous cost and schedule impact analysis?
- Have subsurface investigations been detailed enough to minimize surprises?
- Is there transparent stakeholder communication regarding scope changes?