Case Study: Cost Overrun from Environmental Mitigation on Portland Light Rail Expansion (Portland, OR, 2017)
Project Overview
• Name: Portland Light Rail Expansion – South Corridor
• Location: Portland, Oregon
• Year: 2017
• Project Size: $450 million
• Scope: Construction of new light rail tracks, stations, and supporting infrastructure through environmentally sensitive areas
• Lead Agencies/Contractors:
Category of the Issue, Problem, or Challenge
• Environmental Compliance
• Cost Management
Summary of the Issue, Problem, or Challenge
Unanticipated environmental mitigation requirements discovered mid-construction increased project costs substantially.
Root Cause Analysis
- Incomplete Environmental Assessments: Initial environmental impact studies missed critical species habitats.
- Regulatory Revisions: New mitigation requirements issued during construction.
- Scope Expansion: Added construction of wildlife crossings and habitat restoration areas.
- Delayed Approvals: Permitting delays caused schedule impacts and cost increases.
Impacts Due to the Issue, Problem, or Challenge
- Cost overruns estimated at 14%.
- Schedule extended by six months.
- Increased project complexity and stakeholder scrutiny.
Corrective Actions Taken
- Enhanced environmental survey procedures early in project planning.
- Established dedicated environmental compliance teams.
- Improved coordination with regulatory agencies to anticipate changes.
- Included environmental contingencies in project budgets.
Lessons Learned
- Thorough environmental assessments are critical before construction.
- Regulatory environments can change and impact cost/schedule.
- Early, ongoing agency coordination reduces surprises.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are environmental surveys comprehensive and current?
- Is there active engagement with regulators during construction?
- Are contingency funds allocated for environmental risks?