Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Chicago Deep Tunnel System Expansion
Location: Chicago, Illinois
Year: 2008
Project Size: $1.4 billion
Scope: Construction of underground stormwater tunnels to reduce flooding
Lead Agencies/Contractors: Metropolitan Water Reclamation District of Greater Chicago /


Category of the Issue, Problem, or Challenge
• Quantity Estimation
• Cost Management


Summary of the Issue, Problem, or Challenge
Underestimation of excavation and concrete quantities led to significant cost overruns as actual volumes exceeded initial projections.


Root Cause Analysis

  • Inadequate Survey Data: Initial site surveys lacked detail leading to optimistic quantity assumptions.
  • Geological Variability: Unexpected soil and rock conditions increased excavation volumes.
  • Estimation Methodology: Use of outdated unit rates and insufficient cross-checks.
  • Contractor Input: Limited involvement of contractors during estimation phase reduced accuracy.

Impacts Due to the Issue, Problem, or Challenge

  • Cost overruns of about 16%.
  • Project schedule extended by five months.
  • Increased disputes and claims over quantities and payments.

Corrective Actions Taken

  1. Implemented detailed geotechnical and topographical surveys pre-bid.
  2. Adopted collaborative estimating involving contractors and engineers.
  3. Used updated unit cost databases reflecting current market conditions.
  4. Instituted periodic quantity re-measurements and adjustments during construction.

Lessons Learned

  • Accurate and detailed surveys are essential for reliable quantity estimates.
  • Collaboration during estimation improves accuracy and reduces disputes.
  • Ongoing measurement and adjustment controls cost impacts.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are site surveys detailed and recent?
  • Is contractor input integrated into estimation?
  • Are quantity measurements updated during construction?