Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: New Orleans Levee System Upgrade
Location: New Orleans, Louisiana
Year: 2013
Project Size: $600 million
Scope: Strengthening and rebuilding levees and flood barriers
Lead Agencies/Contractors: U.S. Army Corps of Engineers /


Category of the Issue, Problem, or Challenge
• Supply Chain
• Project Delay


Summary of the Issue, Problem, or Challenge
Disruptions in the supply of key materials, including specialty concrete and steel, caused prolonged project delays.


Root Cause Analysis

  • Single Supplier Dependence: Overreliance on a limited number of suppliers.
  • Transportation Bottlenecks: Port delays and logistics issues impacted material delivery.
  • Market Demand Spikes: Regional construction booms created material shortages.
  • Lack of Inventory Buffers: Minimal on-site stock of critical materials.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 6 months.
  • Increased costs due to expedited shipping and substitute materials.
  • Contractor claims related to schedule impacts.

Corrective Actions Taken

  1. Diversified supplier base to reduce risk.
  2. Improved supply chain visibility and tracking.
  3. Increased on-site material inventories as buffers.
  4. Coordinated logistics planning with suppliers and transport agencies.

Lessons Learned

  • Supply chain robustness is key to schedule adherence.
  • Early procurement and inventory buffers mitigate disruptions.
  • Active supplier and logistics management improve reliability.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is the supply chain diversified and robust?
  • Are material inventories adequate for critical items?
  • Is logistics and supplier communication proactive and effective?