Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Minneapolis Light Rail Transit Extension
Location: Minneapolis, Minnesota
Year: 2014
Project Size: $450 million
Scope: Construction of new light rail tracks and stations
Lead Agencies/Contractors: Metropolitan Council /


Category of the Issue, Problem, or Challenge
• Weather Impacts
• Project Delay


Summary of the Issue, Problem, or Challenge
Extended periods of severe winter weather and early spring flooding delayed earthworks and track laying activities.


Root Cause Analysis

  • Unseasonably Harsh Winter: Snow and freezing conditions persisted longer than historical averages.
  • Flooding in Construction Zones: Spring meltwater caused waterlogging and erosion.
  • Limited Weather Contingency Planning: Project schedule did not fully incorporate weather risks.
  • Equipment Limitations: Some construction equipment was not suitable for wet/frozen conditions.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 6 months in earthworks and track installation.
  • Increased costs for weather mitigation and equipment rentals.
  • Rescheduling impacts on subsequent project phases.

Corrective Actions Taken

  1. Integrated advanced weather forecasting into schedule risk management.
  2. Procured all-weather construction equipment and materials.
  3. Developed contingency plans for weather-related disruptions.
  4. Adjusted project timelines to better reflect regional climate risks.

Lessons Learned

  • Weather risk must be a core element of project planning.
  • Equipment must match environmental conditions.
  • Proactive contingency and mitigation plans reduce delays and costs.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is weather risk quantified and planned for?
  • Are appropriate equipment and materials used for expected conditions?
  • Are contingency plans for weather events integrated into schedules?