Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Dallas Flood Control and Drainage Improvements
Location: Dallas, Texas
Year: 2018
Project Size: $350 million
Scope: Construction of flood control channels and stormwater infrastructure
Lead Agencies/Contractors: City of Dallas /


Category of the Issue, Problem, or Challenge
• Design / Scope Change
• Project Delay


Summary of the Issue, Problem, or Challenge
Significant design changes prompted by updated hydrological data led to rework and schedule setbacks.


Root Cause Analysis

  • Incomplete initial hydrological modeling.
  • New flood data released mid-construction requiring scope changes.
  • Inadequate design flexibility to accommodate changes.
  • Slow approval of revised designs and contractor change orders.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 6 months.
  • Cost increases from rework and extended mobilization.
  • Contractor claims and disputes over schedule impacts.

Corrective Actions Taken

  1. Improved hydrological studies and modeling in early project phases.
  2. Established design contingency allowances and flexible contract terms.
  3. Streamlined design approval and change order processes.
  4. Enhanced communication and collaboration between design and construction teams.

Lessons Learned

  • Accurate and complete initial data reduces mid-project design changes.
  • Flexible contracts and contingency planning accommodate unavoidable changes.
  • Timely approval processes minimize delay impacts.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are baseline data and models robust and validated?
  • Is there contractual flexibility for design changes?
  • Are design revisions and approvals expedited?