Case Study: Delay Due to Utility Relocation Conflicts on Chicago Subway Project (Illinois, 2016)
Project Overview
• Name: Chicago Subway Extension
• Location: Chicago, Illinois
• Year: 2016
• Project Size: $900 million
• Scope: Extension of urban subway tunnels and stations
• Lead Agencies/Contractors: Chicago Transit Authority (CTA) /
Category of the Issue, Problem, or Challenge
• Utility Relocation
• Project Delay
Summary of the Issue, Problem, or Challenge
Unexpected utility conflicts with water, gas, and telecom lines caused work stoppages and redesign efforts.
Root Cause Analysis
- Incomplete Utility Mapping: Existing utility records were outdated or inaccurate.
- Poor Coordination: Limited early engagement with utility companies.
- Complex Urban Environment: Dense infrastructure made relocation challenging.
- Approval Bottlenecks: Utility relocation permits and coordination took longer than anticipated.
Impacts Due to the Issue, Problem, or Challenge
- Delay of 7 months.
- Increased costs for redesign and utility relocation work.
- Schedule disruptions across multiple construction packages.
Corrective Actions Taken
- Conducted detailed utility surveys prior to construction.
- Established early coordination committees with utility providers.
- Streamlined permitting and approval processes for relocations.
- Integrated utility relocation sequencing tightly with construction schedule.
Lessons Learned
- Accurate utility data is essential for urban infrastructure projects.
- Early and ongoing utility coordination reduces conflicts and delays.
- Streamlined processes accelerate utility relocation.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are utility maps verified and updated before construction?
- Is there early and continuous engagement with utility owners?
- Are utility relocation permits planned and tracked effectively?