Project Overview
Name: Second Avenue Subway Phase 2
Location: Manhattan, New York City, New York
Year: 2018
Project Size: $6 billion (overall phase)
Scope: Underground tunnel boring and station excavation in dense urban environment
Lead Agencies/Contractors: Metropolitan Transportation Authority (MTA) /


Category of the Issue, Problem, or Challenge
• Geotechnical
• Differing Site Conditions


Summary of the Issue, Problem, or Challenge
Unexpected variations in soil composition and presence of undocumented underground utilities caused delays and redesign during tunnel excavation.


Root Cause Analysis

  • Incomplete mapping of underground utilities and soil variability in pre-construction phase.
  • Limited geotechnical data in complex urban subsurface.
  • Inadequate coordination with utility owners and agencies.
  • Contractual ambiguity regarding subsurface utility conflicts.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 7 months due to utility relocations and redesign of tunnel support systems.
  • Increased costs for utility coordination, remediation, and additional monitoring.
  • Elevated risk of utility strikes and associated safety hazards.

Corrective Actions Taken

  1. Enhanced utility mapping using electromagnetic and ground-penetrating radar surveys.
  2. Established a dedicated utility coordination task force.
  3. Revised tunnel design to accommodate soil variability and utility conflicts.
  4. Updated contract clauses to clearly address utility conflicts and associated costs.

Lessons Learned

  • Urban subsurface investigations must include comprehensive utility mapping.
  • Early coordination with utility providers prevents costly delays.
  • Contractual clarity on differing site conditions including utilities is critical.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is subsurface utility mapping thorough and up to date?
  • Are communication protocols with utility owners established?
  • Are contracts explicit about responsibilities for utility-related delays?