Case Study: Electrical Subcontractor Delays Cause Power System Installation Setbacks in California (2019)
Project Overview
• Name: San Francisco Bay Bridge Retrofit
• Location: San Francisco, California
• Year: 2019
• Project Size: $520 million
• Scope: Bridge seismic retrofit and electrical system upgrades
• Lead Agencies/Contractors: California DOT /
Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Scheduling & Coordination
Summary of the Issue, Problem, or Challenge
The electrical subcontractor missed key deadlines due to labor shortages and procurement delays, causing a 6-week setback in power system installation.
Root Cause Analysis
- Underestimation of labor and material needs.
- Ineffective subcontractor staffing and recruitment.
- Delays in ordering long-lead electrical components.
- Insufficient coordination with prime contractor schedule.
Impacts Due to the Issue, Problem, or Challenge
- Schedule delay impacting subsequent testing and commissioning.
- Increased project overhead and potential liquidated damages.
- Stakeholder dissatisfaction and increased risk of contractual disputes.
Corrective Actions Taken
- Revised subcontractor resource planning and hiring strategies.
- Accelerated procurement processes with vendor collaboration.
- Improved schedule integration and monitoring.
- Established contingency labor pools and material backups.
Lessons Learned
- Accurate labor and material planning is essential for schedule adherence.
- Early procurement of long-lead items mitigates delays.
- Ongoing communication between subcontractors and prime contractor enhances coordination.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Is subcontractor labor adequately planned and monitored?
- Are procurement lead times considered and managed?
- Is schedule coordination between all parties regularly reviewed?