Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Houston Bayou Flood Control System
Location: Houston, Texas
Year: 2023
Project Size: $320 million
Scope: Construction of floodwalls, pump stations, and stormwater infrastructure
Lead Agencies/Contractors: Harris County Flood Control District /


Category of the Issue, Problem, or Challenge
• Supply Chain Disruption
• Concrete Materials – Admixtures


Summary of the Issue, Problem, or Challenge
The project faced delays when key concrete admixtures used for high-performance concrete mixes were unavailable due to supply interruptions from chemical manufacturers impacted by raw material shortages and transportation bottlenecks.


Root Cause Analysis

  • Raw chemical shortages at primary admixture suppliers.
  • Transportation delays due to regional weather events and driver shortages.
  • Lack of diversified supplier base for admixtures.
  • Inadequate early procurement planning and risk assessment.

Impacts Due to the Issue, Problem, or Challenge
• 2.5-month delay in critical concrete pours for floodwall segments.
• Increased costs due to sourcing from alternate, more expensive suppliers (~$1.5 million).
• Schedule ripple effects impacting subsequent mechanical and electrical work.


Corrective Actions Taken

  1. Developed multiple supply contracts for chemical admixtures.
  2. Increased inventory buffers and early procurement of concrete additives.
  3. Established real-time supply chain monitoring with suppliers.

Lessons Learned

  • Critical chemical admixtures require supply chain risk management equivalent to major structural materials.
  • Early supplier engagement and multi-sourcing reduce risk.
  • Supply chain visibility is key to proactive mitigation.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are admixture suppliers diversified and capacity vetted?
  • Are supply chain risks regularly reviewed and contingency plans in place?
  • Is there sufficient inventory to cover schedule fluctuations?