Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-405 Widening Project
Location: Orange County, California
Year: 2015
Project Size: $1.9 billion
Scope: Expansion of I-405 freeway, including HOV and general-purpose lanes
Lead Agencies/Contractors: Orange County Transportation Authority (OCTA), OC405 Partners


Category of the Issue, Problem, or Challenge
• Contract Change Order
• Utility Coordination


Summary of the Issue, Problem, or Challenge
During construction, delays in utility relocations (by third-party providers) led to a domino effect of change orders related to rescheduling, resequencing of work, and added site safety measures. The contract lacked mechanisms to manage third-party delays effectively.


Root Cause Analysis

  • Poor initial coordination with utility owners.
  • Change orders required for resequencing work zones.
  • Weak contract clauses around third-party impacts.
  • Cost escalation due to prolonged standby time and idle equipment.

Impacts Due to the Issue, Problem, or Challenge
• Project delay of 7 months.
• Change order costs exceeding $45 million.
• Strained relationships between agency and contractor.


Corrective Actions Taken

  1. Added utility relocation buffers in future schedules.
  2. Negotiated stronger utility coordination clauses in future contracts.
  3. Required early-stage utility verification and risk planning.
  4. Created escalation path for third-party intervention by the agency.

Lessons Learned

  • Utility impacts must be clearly addressed contractually.
  • Early utility mapping reduces change orders downstream.
  • Time buffers and resequencing protocols improve flexibility.
  • Clear agency roles in third-party issues can prevent litigation.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are utility risks and schedules well-defined?
  • Do contracts address third-party coordination delays?
  • Are schedule buffers in place for utility conflicts?
  • Is there a clear escalation and intervention process?