Case Study: I-405 Widening Project – Change Order Cascade from Utility Relocation Delays (2015)
Project Overview
• Name: I-405 Widening Project
• Location: Orange County, California
• Year: 2015
• Project Size: $1.9 billion
• Scope: Expansion of I-405 freeway, including HOV and general-purpose lanes
• Lead Agencies/Contractors: Orange County Transportation Authority (OCTA), OC405 Partners
Category of the Issue, Problem, or Challenge
• Contract Change Order
• Utility Coordination
Summary of the Issue, Problem, or Challenge
During construction, delays in utility relocations (by third-party providers) led to a domino effect of change orders related to rescheduling, resequencing of work, and added site safety measures. The contract lacked mechanisms to manage third-party delays effectively.
Root Cause Analysis
- Poor initial coordination with utility owners.
- Change orders required for resequencing work zones.
- Weak contract clauses around third-party impacts.
- Cost escalation due to prolonged standby time and idle equipment.
Impacts Due to the Issue, Problem, or Challenge
• Project delay of 7 months.
• Change order costs exceeding $45 million.
• Strained relationships between agency and contractor.
Corrective Actions Taken
- Added utility relocation buffers in future schedules.
- Negotiated stronger utility coordination clauses in future contracts.
- Required early-stage utility verification and risk planning.
- Created escalation path for third-party intervention by the agency.
Lessons Learned
- Utility impacts must be clearly addressed contractually.
- Early utility mapping reduces change orders downstream.
- Time buffers and resequencing protocols improve flexibility.
- Clear agency roles in third-party issues can prevent litigation.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are utility risks and schedules well-defined?
- Do contracts address third-party coordination delays?
- Are schedule buffers in place for utility conflicts?
- Is there a clear escalation and intervention process?