Case Study: I-70 Mountain Corridor Reconstruction – Design-Build Delivery and Environmental Risk Mismanagement (2014)
Project Overview
• Name: I-70 Mountain Corridor Reconstruction
• Location: Colorado
• Year: 2014
• Project Size: $400 million
• Scope: Reconstruction and widening of highway section in environmentally sensitive mountain terrain using Design-Build
• Lead Agencies/Contractors: Colorado Department of Transportation (CDOT), Design-Build Contractor
Category of the Issue, Problem, or Challenge
• Project Delivery Method
• Design-Build
Summary of the Issue, Problem, or Challenge
During construction, environmental permitting delays and unforeseen environmental mitigation requirements slowed work. The Design-Build contract did not adequately allocate risks or schedule contingencies for environmental uncertainties, causing cost overruns and schedule slips.
Root Cause Analysis
- Insufficient environmental risk assessment during design phase.
- Contract ambiguity regarding responsibility for environmental delays.
- Overly aggressive schedule without adequate contingency for environmental permitting.
- Limited early stakeholder engagement with environmental regulators.
Impacts Due to the Issue, Problem, or Challenge
• Schedule delay of 4 months.
• Cost overruns totaling $12 million.
• Increased friction between contractor, owner, and regulators.
Corrective Actions Taken
- Revised contract clauses to clarify environmental risk allocation.
- Enhanced early engagement with regulatory agencies.
- Added schedule buffers for environmental permit reviews.
- Implemented joint risk management sessions including environmental stakeholders.
Lessons Learned
- Environmental risks must be thoroughly assessed early and allocated clearly in contracts.
- Early and proactive engagement with regulators reduces surprises.
- Schedules must realistically incorporate environmental permitting timelines.
- Joint risk management improves coordination and transparency.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are environmental risks fully assessed pre-construction?
- Is contract language clear on environmental delay responsibilities?
- Is schedule realistic for environmental permitting?
- Are regulators engaged early and continuously?