Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-95 Express Lanes Expansion
Location: Virginia
Year: 2017
Project Size: $750 million
Scope: Expansion of express toll lanes on I-95 using Design-Build delivery
Lead Agencies/Contractors: Virginia Department of Transportation (VDOT), Design-Build Joint Venture


Category of the Issue, Problem, or Challenge
• Project Delivery Method
• Design-Build


Summary of the Issue, Problem, or Challenge
The project encountered construction delays and cost overruns linked to unclear risk-sharing clauses in the Design-Build contract. Disputes arose over unforeseen geotechnical conditions and utility relocations, impacting the project’s schedule and budget.


Root Cause Analysis

  • Ambiguous contract language on risk allocation for subsurface conditions.
  • Insufficient pre-construction site investigation.
  • Lack of a formal dispute resolution process embedded in contract.
  • Delays in utility relocation coordination with third parties.

Impacts Due to the Issue, Problem, or Challenge
• Schedule delays of 5 months.
• Cost overruns approximately $30 million.
• Increased conflict and claims between owner and contractor.


Corrective Actions Taken

  1. Clarified contract language related to geotechnical risk and utility coordination.
  2. Improved site investigation protocols pre-construction.
  3. Established formal dispute resolution procedures.
  4. Enhanced coordination processes with utility companies.

Lessons Learned

  • Clear risk allocation is critical in Design-Build projects.
  • Comprehensive site investigations reduce surprises.
  • Defined dispute resolution mechanisms improve issue management.
  • Early utility coordination prevents delays.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is risk allocation for subsurface and utilities clear?
  • Has the site been adequately investigated pre-construction?
  • Are dispute resolution methods defined contractually?
  • Is there an early and effective utility coordination plan?