Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Miami Port Tunnel
Location: Miami, Florida
Year: 2010
Project Size: $667 million
Scope: Design and construction of a deep-bore tunnel connecting the Port of Miami to the interstate highway system
Lead Agencies/Contractors: Florida DOT /


Category of the Issue, Problem, or Challenge
• Design
• Tunnel Engineering


Summary of the Issue, Problem, or Challenge
Mid-construction design changes to accommodate unforeseen underground utilities and updated ventilation requirements resulted in significant scope expansion. The changes caused delays and increased costs due to re-design and additional construction work.


Root Cause Analysis

  • Incomplete underground utility mapping prior to design completion.
  • Late integration of updated environmental and safety ventilation standards.
  • Insufficient contingency planning for utility conflicts.
  • Delayed coordination between design teams and utility providers.

Impacts Due to the Issue, Problem, or Challenge
• Schedule delays of 6 months.
• Cost overruns approximated at $18 million.
• Disruptions in utility service and stakeholder dissatisfaction.


Corrective Actions Taken

  1. Enhanced subsurface utility engineering (SUE) investigations during design.
  2. Established formal coordination processes with utility companies.
  3. Included contingency buffers in schedule and budget for design changes.
  4. Upgraded ventilation system design early with stakeholder input.

Lessons Learned

  • Comprehensive subsurface investigations reduce utility conflict risks.
  • Early and ongoing coordination with utility providers is critical.
  • Contingency planning for design changes is essential in complex environments.
  • Regulatory and safety standards updates must be integrated promptly.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has a thorough subsurface utility investigation been completed?
  • Are utility providers engaged early in the design process?
  • Are contingency buffers included for potential design changes?
  • Are ventilation and safety standards updated and incorporated timely?