Project Overview
Name: Minneapolis Green Line Light Rail Transit
Location: Minneapolis, Minnesota
Year: 2011
Project Size: $957 million
Scope: Construction of a light rail transit corridor including tracks, stations, and utilities
Lead Agencies/Contractors: Metropolitan Council /


Category of the Issue, Problem, or Challenge
• Design
• Construction Interface


Summary of the Issue, Problem, or Challenge
Discrepancies between design specifications and field conditions led to multiple redesigns during construction, especially in utility relocations and track alignment, causing delays and cost increases.


Root Cause Analysis

  • Incomplete field surveys and utility documentation during design.
  • Poor coordination between design teams and utility providers.
  • Lack of detailed constructability reviews prior to finalizing design.
  • Communication gaps between design engineers and construction contractors.

Impacts Due to the Issue, Problem, or Challenge
• Construction schedule extended by 8 months.
• Cost overruns of approximately $12 million.
• Stakeholder frustration due to frequent design changes.


Corrective Actions Taken

  1. Conducted updated field surveys and utility mapping.
  2. Improved collaboration between design teams and utility companies.
  3. Implemented detailed constructability reviews before design finalization.
  4. Established direct communication channels between designers and contractors.

Lessons Learned

  • Thorough field verification reduces risk of design-field discrepancies.
  • Early utility coordination is essential in urban projects.
  • Constructability reviews identify potential conflicts early.
  • Open communication improves responsiveness to unforeseen issues.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has field verification been thoroughly completed before design?
  • Are utility providers engaged early and regularly?
  • Are constructability reviews embedded in the design process?
  • Is communication between design and construction teams direct and frequent?