Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: New Jersey Turnpike Widening
Location: New Jersey
Year: 2013
Project Size: $1.5 billion
Scope: Widening of New Jersey Turnpike using Design-Bid-Build delivery
Lead Agencies/Contractors: New Jersey Turnpike Authority, Multiple Contractors


Category of the Issue, Problem, or Challenge
• Project Delivery Method
• Design-Bid-Build


Summary of the Issue, Problem, or Challenge
During construction, numerous change orders due to design omissions and unforeseen subsurface conditions led to cost escalation and delays. The traditional delivery method lacked flexibility in managing these changes effectively.


Root Cause Analysis

  • Incomplete design documentation before bidding.
  • Poor geotechnical site investigations.
  • Rigid contract change order processes.
  • Fragmented communication between designer and contractor.

Impacts Due to the Issue, Problem, or Challenge
• Project delay of 9 months.
• Cost overruns exceeding $70 million.
• Increased contractor claims and disputes.


Corrective Actions Taken

  1. Enhanced design completeness before bidding.
  2. Improved site investigation standards.
  3. Streamlined change order approval workflows.
  4. Fostered closer designer-contractor collaboration.

Lessons Learned

  • Comprehensive design reduces change orders.
  • Rigorous site investigations are critical.
  • Flexible change management processes improve delivery.
  • Strong communication between design and construction teams mitigates risks.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is design documentation fully complete before bidding?
  • Are site investigations sufficiently thorough?
  • Are change order procedures flexible and efficient?
  • Is there ongoing collaboration between design and construction?