Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: US-95 Corridor Safety Enhancements
Location: Clark County, Nevada
Year: 2018
Project Size: $270 million
Scope: Retaining walls, culverts, and safety barrier systems for highway widening
Lead Agencies/Contractors: Nevada DOT (Owner) /


Category of the Issue, Problem, or Challenge
• Contract Owner
• Material Specification & Procurement


Summary of the Issue, Problem, or Challenge
Mid-project, the owner directed substitution of reinforced concrete block materials to reduce cost. Within weeks of installation, cracking and deformation were observed in completed retaining wall sections.


Root Cause Analysis

  • Substituted blocks had lower compressive strength than originally specified.
  • No re-analysis of wall design to accommodate change.
  • Owner skipped independent material performance testing.

Impacts Due to the Issue, Problem, or Challenge

  • Partial removal and rebuild of over 1,200 feet of retaining walls.
  • Schedule setback of 4.5 months.
  • $6.5 million cost increase, borne partially by the owner.

Corrective Actions Taken

  1. Reinstated performance-based specifications with third-party testing.
  2. Material substitutions now require contractor and engineering team concurrence.
  3. NDOT revised its internal approval workflows for design changes.

Lessons Learned

  • Material substitutions must undergo technical evaluation and design verification.
  • Cost savings should not compromise structural integrity.
  • Owner-led changes must follow documented engineering sign-off protocols.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has the proposed material been tested and verified for performance equivalency?
  • Was the structural design reviewed for compatibility with material changes?
  • Are all change directives documented and traceable to engineering approvals?