Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Green River Covered Bridge Replacement
Location: Guilford, Vermont
Year: 2020
Project Size: $24 million
Scope: Demolition and replacement of historic covered bridge with flood-resistant structure
Lead Agencies/Contractors: Vermont Agency of Transportation (VTrans), Federal Highway Administration (Owner) /


Category of the Issue, Problem, or Challenge
• Contract Owner
• Regulatory Compliance (NEPA, Section 106)


Summary of the Issue, Problem, or Challenge
Construction began before the Section 106 historic preservation process was fully completed. Legal challenges forced a shutdown just days after demolition started.


Root Cause Analysis

  • Owner agency misjudged requirement for consulting with historical societies.
  • Failure to document mitigation plans for cultural heritage impacts.
  • NEPA and Section 106 processes were not fully harmonized.

Impacts Due to the Issue, Problem, or Challenge

  • Legal injunction halted construction for 4 months.
  • Temporary bridge required for detour, increasing costs by $2.7 million.
  • National media attention and community backlash.

Corrective Actions Taken

  1. VTrans retrained staff on federal preservation law compliance.
  2. Project development flow was restructured to prevent NTP before environmental clearance.
  3. Mitigation agreements with historical agencies became standard protocol.

Lessons Learned

  • Owners must comply with federal historic and environmental regulations before work begins.
  • Early engagement with stakeholders reduces legal and reputational risk.
  • Regulatory coordination must be integrated into early project planning.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has the project received full environmental and cultural clearance before construction?
  • Are all required federal and state agencies formally consulted?
  • Is there documentation of stakeholder agreements on mitigation?