Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Jane Byrne Interchange Reconstruction
Location: Chicago, Illinois
Year: 2016
Project Size: $800 million
Scope: Multi-phase urban interchange reconfiguration under live traffic conditions
Lead Agencies/Contractors: Illinois Department of Transportation (IDOT) /


Category of the Issue, Problem, or Challenge
• Contract Owner
• Construction Sequencing & Phasing


Summary of the Issue, Problem, or Challenge
The owner-mandated phasing sequence did not account for construction logistics and site access limitations, leading to rework and material handling inefficiencies.


Root Cause Analysis

  • Owner prioritized traffic flow over construction feasibility without contractor input.
  • Initial phasing did not reflect physical constraints for equipment maneuvering.
  • Early contractor involvement (ECI) was not used despite project complexity.

Impacts Due to the Issue, Problem, or Challenge

  • Over 200 days of cumulative delays across three prime contracts.
  • More than $20 million in change orders due to re-staging and traffic control revisions.
  • Damage to IDOT’s public perception and political scrutiny.

Corrective Actions Taken

  1. Phasing plans for future projects required validation by contractor means-and-methods experts.
  2. IDOT created an internal constructability review team to vet all complex phasing.
  3. Traffic management and construction schedules now developed in parallel.

Lessons Learned

  • Owner-imposed phasing must be grounded in construction reality.
  • Early contractor involvement can reduce constructability risks.
  • Urban infrastructure projects demand dynamic and collaborative planning.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has the construction phasing been reviewed from a logistics and field feasibility perspective?
  • Were contractors engaged early in phasing development?
  • Are there mechanisms for revising traffic control plans as field conditions evolve?