Case Study: Owner-Prescribed Construction Phasing Conflicts with Field Realities in Illinois (2016)
Project Overview
• Name: Jane Byrne Interchange Reconstruction
• Location: Chicago, Illinois
• Year: 2016
• Project Size: $800 million
• Scope: Multi-phase urban interchange reconfiguration under live traffic conditions
• Lead Agencies/Contractors: Illinois Department of Transportation (IDOT) /
Category of the Issue, Problem, or Challenge
• Contract Owner
• Construction Sequencing & Phasing
Summary of the Issue, Problem, or Challenge
The owner-mandated phasing sequence did not account for construction logistics and site access limitations, leading to rework and material handling inefficiencies.
Root Cause Analysis
- Owner prioritized traffic flow over construction feasibility without contractor input.
- Initial phasing did not reflect physical constraints for equipment maneuvering.
- Early contractor involvement (ECI) was not used despite project complexity.
Impacts Due to the Issue, Problem, or Challenge
- Over 200 days of cumulative delays across three prime contracts.
- More than $20 million in change orders due to re-staging and traffic control revisions.
- Damage to IDOT’s public perception and political scrutiny.
Corrective Actions Taken
- Phasing plans for future projects required validation by contractor means-and-methods experts.
- IDOT created an internal constructability review team to vet all complex phasing.
- Traffic management and construction schedules now developed in parallel.
Lessons Learned
- Owner-imposed phasing must be grounded in construction reality.
- Early contractor involvement can reduce constructability risks.
- Urban infrastructure projects demand dynamic and collaborative planning.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Has the construction phasing been reviewed from a logistics and field feasibility perspective?
- Were contractors engaged early in phasing development?
- Are there mechanisms for revising traffic control plans as field conditions evolve?