Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Bluestone Dam Reinforcement Phase III
Location: Hinton, West Virginia
Year: 2021
Project Size: $190 million
Scope: Seismic and structural retrofitting of aging dam structure
Lead Agencies/Contractors: U.S. Army Corps of Engineers (Owner) /


Category of the Issue, Problem, or Challenge
• Contract Owner
• Schedule and Risk Allocation


Summary of the Issue, Problem, or Challenge
Despite heavy and abnormal rainfall impacting access to foundation areas, the owner declined to grant weather-related time extensions, asserting that weather risk was contractor-held per the contract terms.


Root Cause Analysis

  • Strict contract terms assigning weather delays to contractor risk.
  • Owner unwilling to adjust milestones despite documented force majeure.
  • Lack of mutual risk-sharing provisions in original contract.

Impacts Due to the Issue, Problem, or Challenge

  • Contractor forced to accelerate work during unsafe or inefficient conditions.
  • Quality issues emerged due to rushed execution.
  • Dispute escalated to claim arbitration over 85 weather-impacted days.

Corrective Actions Taken

  1. Army Corps reviewed and modified weather risk language in future contracts.
  2. Implemented weather escalation clauses tied to historical averages.
  3. Improved site-specific risk assessments during pre-bid phase.

Lessons Learned

  • Rigid contract terms can lead to unfair and unproductive risk burdens.
  • Weather risk allocation should be realistic and balanced.
  • Early and equitable resolution of weather impacts protects all parties.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are weather delay provisions aligned with regional conditions?
  • Is there a mechanism to adjust schedules for severe weather?
  • Does the owner have a dispute resolution plan for weather-related claims?