Case Study: Owner Refuses Weather Time Extension on West Virginia Dam Project (2021)
Project Overview
• Name: Bluestone Dam Reinforcement Phase III
• Location: Hinton, West Virginia
• Year: 2021
• Project Size: $190 million
• Scope: Seismic and structural retrofitting of aging dam structure
• Lead Agencies/Contractors: U.S. Army Corps of Engineers (Owner) /
Category of the Issue, Problem, or Challenge
• Contract Owner
• Schedule and Risk Allocation
Summary of the Issue, Problem, or Challenge
Despite heavy and abnormal rainfall impacting access to foundation areas, the owner declined to grant weather-related time extensions, asserting that weather risk was contractor-held per the contract terms.
Root Cause Analysis
- Strict contract terms assigning weather delays to contractor risk.
- Owner unwilling to adjust milestones despite documented force majeure.
- Lack of mutual risk-sharing provisions in original contract.
Impacts Due to the Issue, Problem, or Challenge
- Contractor forced to accelerate work during unsafe or inefficient conditions.
- Quality issues emerged due to rushed execution.
- Dispute escalated to claim arbitration over 85 weather-impacted days.
Corrective Actions Taken
- Army Corps reviewed and modified weather risk language in future contracts.
- Implemented weather escalation clauses tied to historical averages.
- Improved site-specific risk assessments during pre-bid phase.
Lessons Learned
- Rigid contract terms can lead to unfair and unproductive risk burdens.
- Weather risk allocation should be realistic and balanced.
- Early and equitable resolution of weather impacts protects all parties.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Are weather delay provisions aligned with regional conditions?
- Is there a mechanism to adjust schedules for severe weather?
- Does the owner have a dispute resolution plan for weather-related claims?