Case Study: Owner’s Late Design Changes on Bridge Project in Illinois (2020)
Project Overview
• Name: I-74 Mississippi River Bridge Replacement
• Location: Moline, Illinois to Bettendorf, Iowa
• Year: 2020
• Project Size: $1.2 billion
• Scope: Dual-structure cable-stayed bridge with interchanges and pedestrian/bike facilities
• Lead Agencies/Contractors: Illinois DOT, Iowa DOT /
Category of the Issue, Problem, or Challenge
• Contract Owner
• Design Management
Summary of the Issue, Problem, or Challenge
During superstructure work, the owner issued a major design change to accommodate future rail expansion—well after structural steel had been procured. The change required new connection details and longer lead-time fabrication.
Root Cause Analysis
- Design revisions were driven by late-stage interagency agreements.
- Coordination gaps existed between owner planning and active construction.
- The impact of changes on schedule and procurement was underestimated.
Impacts Due to the Issue, Problem, or Challenge
- Steel deliveries delayed by 4 months due to redesign and re-fabrication.
- Temporary work stoppages and rework impacted bridge segmental assembly.
- Claims totaling $11.7 million were filed for delay and remobilization.
Corrective Actions Taken
- Interagency coordination timelines were restructured to front-load all scope impacts.
- Late-stage design changes now trigger formal constructability reviews.
- Future large bridge projects require locking design prior to procurement milestones.
Lessons Learned
- Design lock-in must precede material procurement on megaprojects.
- Owner planning must align with downstream construction impacts.
- Interagency MOUs can create design ripple effects if not timed correctly.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Have all external stakeholder design needs been finalized before bid?
- Is there a formal process for evaluating the construction impact of late design changes?
- Are material procurement triggers aligned with design freeze milestones?