Case Study: Owner’s Scope Creep Disrupts Dam Rehabilitation Project in Pennsylvania (2022)
Project Overview
• Name: Francis E. Walter Dam Safety Upgrade
• Location: White Haven, Pennsylvania
• Year: 2022
• Project Size: $180 million
• Scope: Spillway capacity enhancement, embankment reinforcement, and outlet structure rehabilitation
• Lead Agencies/Contractors: U.S. Army Corps of Engineers (USACE) /
Category of the Issue, Problem, or Challenge
• Contract Owner
• Scope Management
Summary of the Issue, Problem, or Challenge
Midway through construction, USACE introduced a series of “scope refinements” including increased flood control capacity and seismic upgrades. These revisions required redesign of key structural elements and halted active work.
Root Cause Analysis
- Scope growth occurred without contract amendment or schedule relief.
- Owner had evolving stakeholder demands (e.g., FEMA, local communities).
- No formal change management structure in place for post-award revisions.
Impacts Due to the Issue, Problem, or Challenge
- 5-month delay while design teams re-engineered embankment core and spillway profiles.
- Contractor incurred $3.9 million in additional overhead and standby costs.
- Trust issues developed between contractor and federal owner team.
Corrective Actions Taken
- Change control protocol formalized for all future USACE dam projects.
- Contingency budget and float included for owner-requested changes.
- Owner PMs trained in scope discipline and risk-driven decision-making.
Lessons Learned
- Scope changes mid-construction must be treated as formal contract modifications.
- Owner agencies must manage upstream stakeholder alignment prior to NTP.
- Change control discipline is critical to schedule and cost integrity.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Has the owner formally frozen scope prior to bid?
- Are any stakeholder-driven changes required post-NTP contractually accounted for?
- Is there a documented change management process with risk-based approvals?