Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-95 Overpass Rehabilitation
Location: Philadelphia, Pennsylvania
Year: 2014
Project Size: $85 million
Scope: Replacement and rehabilitation of aging overpass decks on I-95
Lead Agencies/Contractors: Pennsylvania Department of Transportation (PennDOT) /


Category of the Issue, Problem, or Challenge
• Structural Failure
• Construction Safety


Summary of the Issue, Problem, or Challenge
During concrete deck placement on an overpass, a section of formwork failed, causing a partial deck collapse. The incident occurred during wet concrete pouring, putting workers at risk and requiring emergency response and cleanup.


Root Cause Analysis

  • Formwork Design Deficiency: Formwork was not adequately designed to support wet concrete weight.
  • Inadequate Bracing and Supports: Temporary shoring was insufficient and improperly installed.
  • Inspection Lapses: Pre-pour inspections did not identify weaknesses in formwork assembly.
  • Poor Communication: Safety warnings from workers were not acted upon in time.

Impacts Due to the Issue, Problem, or Challenge

  • Injuries to two workers, though no fatalities.
  • Project delay due to cleanup and reconstruction.
  • Regulatory investigations and increased scrutiny on formwork safety.

Corrective Actions Taken

  1. Revised formwork design standards with higher safety factors and redundancy.
  2. Mandatory third-party inspection of formwork before concrete placement.
  3. Enhanced worker safety training and incident reporting protocols.
  4. Implementation of real-time monitoring during concrete pours.

Lessons Learned

  • Formwork systems must be designed and inspected to withstand all expected loads.
  • Worker safety concerns should be prioritized with clear communication channels.
  • Real-time monitoring can detect formwork distress before collapse.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Has formwork design been independently reviewed for load capacity?
  • Are inspections conducted before each concrete placement?
  • Is there an effective communication protocol for safety warnings from site workers?