Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Denver Light Rail Expansion
Location: Denver, Colorado
Year: 2018
Project Size: $550 million
Scope: Tunnel construction and shotcrete lining application
Lead Agencies/Contractors: Regional Transportation District (RTD) /


Category of the Issue, Problem, or Challenge
• Quality Control
• Materials
• Structural


Summary of the Issue, Problem, or Challenge
Uneven thickness and poor adhesion of shotcrete layers led to premature spalling and reapplication needs during tunnel lining construction.


Root Cause Analysis

  • Inconsistent shotcrete mix batching and application techniques.
  • Insufficient QC inspection during layering processes.
  • Lack of training for shotcrete operators and supervisors.
  • Poor documentation of quality checks and acceptance criteria.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 4 months due to removal and reapplication of shotcrete.
  • Additional costs in materials and labor.
  • Increased risk of long-term structural problems if not corrected.

Corrective Actions Taken

  1. Standardized shotcrete mix design and batching quality controls.
  2. Increased inspection frequency during application phases.
  3. Implemented training programs for shotcrete crews and QC staff.
  4. Improved QC documentation and reporting systems.

Lessons Learned

  • Consistent material batching and application ensure shotcrete durability.
  • Frequent QC inspections prevent defects.
  • Training enhances operator and inspector effectiveness.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are shotcrete mixes controlled and tested consistently?
  • Is application quality inspected regularly?
  • Are operators and inspectors properly trained?