Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: I-70 Highway Rehabilitation
Location: St. Louis, Missouri
Year: 2017
Project Size: $400 million
Scope: Asphalt pavement overlay and structural repairs
Lead Agencies/Contractors: Missouri Department of Transportation (MoDOT) /


Category of the Issue, Problem, or Challenge
• Quality Control
• Materials


Summary of the Issue, Problem, or Challenge
Non-uniform compaction and temperature control during asphalt overlay led to premature rutting and surface defects.


Root Cause Analysis

  • Inadequate temperature monitoring of asphalt mix during placement.
  • Poor compaction techniques and insufficient roller coverage.
  • Lack of real-time quality control and feedback mechanisms.
  • Insufficient training for paving and QC crews.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 2 months due to corrective milling and repaving.
  • Additional costs for materials and labor.
  • Reduced pavement service life and increased maintenance needs.

Corrective Actions Taken

  1. Installed temperature sensors and monitoring systems during asphalt placement.
  2. Improved compaction procedures with detailed roller coverage plans.
  3. Enhanced QC real-time data collection and crew feedback.
  4. Conducted training sessions focused on asphalt paving best practices.

Lessons Learned

  • Temperature control during placement is crucial for asphalt quality.
  • Thorough compaction and monitoring prevent early failures.
  • Real-time QC and crew training improve pavement outcomes.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is asphalt temperature monitored and controlled continuously?
  • Are compaction techniques documented and verified?
  • Are paving and QC crews trained in best practices?