Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: San Francisco–Oakland Bay Bridge Eastern Span Replacement
Location: San Francisco, California
Year: 2015
Project Size: $6.5 billion
Scope: Pile driving and foundation installation for bridge towers
Lead Agencies/Contractors: Caltrans /


Category of the Issue, Problem, or Challenge
• Quality Control
• Geotechnical


Summary of the Issue, Problem, or Challenge
Incomplete pile embedment and misaligned piles due to inadequate QC inspections caused schedule delays and additional pile driving.


Root Cause Analysis

  • Insufficient real-time monitoring of pile driving depth and alignment.
  • Lack of immediate corrective action procedures when deviations occurred.
  • Inadequate training of pile driving operators and QC inspectors.
  • Poor documentation and communication of pile driving data.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 6 months due to re-driving and correcting misaligned piles.
  • Increased costs for additional equipment and labor.
  • Potential structural risks if uncorrected.

Corrective Actions Taken

  1. Installed advanced pile driving monitoring systems with real-time feedback.
  2. Established immediate response protocols for alignment deviations.
  3. Conducted comprehensive training for operators and inspectors.
  4. Improved data documentation and communication channels.

Lessons Learned

  • Real-time monitoring is vital for pile driving quality.
  • Prompt corrective action prevents compounded errors.
  • Proper training enhances QC effectiveness.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Is pile driving depth and alignment monitored continuously?
  • Are deviations addressed immediately?
  • Are operators and QC staff adequately trained?