Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Houston Flood Control Channel Improvements
Location: Houston, Texas
Year: 2019
Project Size: $400 million
Scope: Construction of stormwater channels and levees
Lead Agencies/Contractors: Harris County Flood Control District /


Category of the Issue, Problem, or Challenge
• Quality Control
• Structural Integrity
• Project Delay


Summary of the Issue, Problem, or Challenge
Inspection failures allowed improperly compacted embankments and substandard concrete pours, compromising channel stability and causing remediation delays.


Root Cause Analysis

  • Gaps in soil compaction testing protocols.
  • Insufficient inspection frequency during concrete pours.
  • Poor communication between QC inspectors and field crews.
  • Inadequate corrective action procedures for detected deficiencies.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 5 months for rework and additional testing.
  • Increased project costs from remediation and extended oversight.
  • Potential risk to flood protection performance if issues were not corrected.

Corrective Actions Taken

  1. Revised and increased testing protocols for soil and concrete.
  2. Improved inspector training and authority to halt work on quality concerns.
  3. Established clear communication channels and immediate corrective action workflows.
  4. Instituted third-party audits to supplement in-house QC.

Lessons Learned

  • Quality control is crucial for infrastructure safety and longevity.
  • Inspector authority and communication improve issue resolution.
  • Third-party audits provide valuable independent assurance.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are inspection and testing protocols comprehensive and followed?
  • Do inspectors have clear authority to stop work for quality concerns?
  • Is there an effective system for immediate corrective actions?