Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Bay Bridge Eastern Span Seismic Retrofit
Location: San Francisco, California
Year: 2021
Project Size: $550 million
Scope: Seismic retrofit involving replacement and reinforcement of critical structural connections
Lead Agencies/Contractors: Caltrans /


Category of the Issue, Problem, or Challenge
• Supply Chain Disruption
• Fasteners and Structural Hardware


Summary of the Issue, Problem, or Challenge
The retrofit project encountered delays when deliveries of high-strength structural bolts were delayed due to a global shortage of alloy steel and manufacturing capacity constraints.


Root Cause Analysis

  • Alloy steel shortages driven by increased demand in automotive and aerospace sectors.
  • Limited number of manufacturers qualified to produce seismic-grade bolts.
  • Insufficient lead time for procurement and qualification of alternate suppliers.
  • Lack of inventory buffers for critical fasteners.

Impacts Due to the Issue, Problem, or Challenge
• 3-month delay in bolting and structural assembly phases.
• Increased costs for rush manufacturing and alternate sourcing (~$1.8 million).
• Potential compromise in schedule for seismic safety certification.


Corrective Actions Taken

  1. Expanded supplier base and qualified alternative bolt manufacturers.
  2. Instituted early procurement protocols for critical hardware.
  3. Maintained safety and quality standards despite schedule pressures.

Lessons Learned

  • Critical structural hardware supply requires early and diversified sourcing.
  • Industry-wide demand fluctuations impact niche construction materials.
  • Quality certification processes must be balanced with schedule pressures.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are critical hardware suppliers diversified and qualified?
  • Are procurement schedules aligned with manufacturing lead times?
  • Is quality certification integrated into procurement and scheduling?